PROJECT MANAGEMENT PROCEDURES

4.1   INTRODUCTION
This section describes methods and procedures for project management comprising project co-ordination, progress reporting, management reviews and review meeting, etc.
4.2   PROJECT EXECUTION METHOD AND MATRIX
This item defines the project organization and the specific responsibilities for each of the areas of services of the Consultant in accordance with the Contract No. ..................
The key areas of the Consultant’s services are:
1)     Contractor Interface - Support to PLN in monitoring, and supervising Contractor's performance in construction and commissioning.
2)     Consultant - PLN Interface – Reporting on Contractor’s progress of work and making recommendations to PLN if necessary
4.2.1       Division of Responsibility
The division of responsibility for the scope of services defined in Construction Supervision and QA/QC in accordance with Contract No. ...................................................................... with PLN .

4.2.2       Key Position Descriptions
The position descriptions of the key members of the Consultant’s team :
-            Project Director
-            Project Manager
-            Boiler/Turbine Engineer
-            BOP Engineer
-            Coal & Ash Handling Engineer
-            Electrical Engineer
-            Instrument &Control Engineer
-            Civil Structure Engineer
-            Chemical / Environmental Engineer
-            Planning / Schedule Engineer
4.3   Interface between Consultant’s Head Office and Site Office
The key interfacing between the Jakarta (Head Office) and the Site Office is achieved by the following:
Consultant’s Project Manager – plays key role in interfacing between Jakarta (Head Office) and Site Office activities and provides coordination and direction as necessary to the personnel at each location.
Coordination Meeting – The Consultant and Site Offices have their own Weekly Coordination Meetings involving PLN, Consultant and the Contractor.
4.4   Interfaces between Contractors
Interface with Contractor shall take place at Site offices independently.  With PLN’s approval, the Consultant’s project team members may also initiate direct contact with the Contractor for expediting any pending issues that need to be resolved in a timely manner.  PLN project team members shall be notified of such direct contact by copy of correspondence, telecom or facsimile communication.
4.5   Interfaces between PLN Organizations
Standard interfacing among PLN organizations is through normal exchange of correspondence and documents in accordance with BASCOM.  Special interfacing if necessary between different PLN entities will be initiated by PLN Pusat, PLN E, PLN Pikitring SUAR or PLN Site depending on nature of interface and the corresponding responsible PLN entity. Refer to BASCOM Exhibit as below
4.6   Engineer Site Activities and Meeting
The Consultants Engineer (project team) has activities involving Inspectors to monitoring and makes comments to the contractor’s activities against day by day and will support to PLN Site and Project Manager. The form of Engineer activities show in Appendix 4.1
4.7   Weekly meeting 
The purpose of discussed site maters the consultant Engineer lead weekly meeting regularly in every week involving PLN Site, Consultant and Contractor at PLN site office. The form of weekly meeting show. The form weekly meeting show in Appendix 4.2
4.8  Monthly Progress Report
This section describes responsibility, issue schedule and contents of the Monthly Progress Reports to report progress of the Consultant’s work to PLN.
4.8.1       Responsibility
The Project Manager is responsible for the issue of the Monthly Progress Report
4.8.2       Issue Schedule
The monthly report details activities for the period of the previous month.  The monthly report shall be issued by the Project Manager by the end of the following month if required
4.8.3       Content
Content of Monthly Progress Report show in Appendix 4.3
4.9  QUATERLY PROGRESS REPORT
Every third month, a quarterly Progress Report shall be issued by the end of the following month.
The report shall cover all activities during the quarter and be issued in a similar way as the Monthly Report described in item 7 above
4.10  REVIEW OF CONTRACTORS PROGRESS REPORT
The Consultant shall review the Contractor’s monthly report and provide PLN with comments for further action.
4.11  PROJECT COORDINATION MEETING
Following issues shall be addressed in the Project Coordination Meeting to be held every other month at PLN Pembangkitan Sumatera I and or PLN Head Office Jakarta and or PLN site.
-      Contractor’s progress and performance
-      Technical matters related Construction and or Engineering if necessary
-      Special problems, if any
The form weekly meeting show in Appendix 4.4
4.12  ASSIGNMENT OF PERSONEL
The Consultant’s personnel shall be assigned to the project. 
5.    ADMINISTRASION PROCEDURES
5.1    GENERAL
5.1.1         Purpose
This procedure is written with the aim of ensuring that information is channeled in an appropriate manner. This procedure details administrative functions associated with project communications.  It does not apply to Contractor’s engineering documents or to minutes of meeting.
5.1.2         Scope and Application
This procedure covers all forms of internal and external communications and applies to all members of the Project.
The communication procedure applies to letters, correspondence, transmittal, telephone communications between PLN Site and the Consultants included PLN organizations, project team members and other correspondence associated with the Project and proceed at the Construction Site Office.
The control of communications is described in Appendix 5.1 and in the Communication Control Register Instruction Manual for the Project
This communication procedure does not apply to the Contractor’s engineering documents such as design drawings, specifications and calculations, which are controlled by the Design Document Register. 
5.1.3         Updating and Issue
Updating and review of this procedure shall be under-taken by the Project Manager as and when it is necessary.
5.2.  DISTRIBUTION
5.2.1         Minimum Distribution
Originators or recipients of correspondence, telexes, minutes of telephone call, etc. shall ensure that copies are distributed as shown on the "BASCOM" sheet show in Appendix 5.1
5.2.2         Additional Distribution
5.3    RESPONSIBILITY
The Project Administrators involving Secretary who are in charge of the Communication Control Register (Project Team) in the Project Site Office, respectively shall be responsible for processing and controlling the project correspondence, including distributing, retrieving and maintaining the Project record files as well as reference files.
5.4   STANDARD FORM
The Project standard communication forms are shown in Appendix 5.2 the Site Office Project Standard Form respectively.
5.5   COMMUNICATION PROCEDURE
This section describes correspondence procedure for the Project correspondence with the Contractor at the Site Office, correspondence between PLN and the Consultants.
5.6   SITE OFFICE CORRESPONDENCE
5.6.1         OUTGOING LETTERS
a)         Formats
The outgoing Site Office correspondence shall follow the sample letter formats and letterhead in Appendix 5.2 Control Numbers
All the outgoing letters from PLN Site to the Contractor shall have a PLN Site stamp if any and PLN Site control number as well as a central communication control number assigned by the Communication Control Register. 
b)         Distribution
Distribution shall follow the requirements of BASCOM in Appendix 5.1 or as directed by the originator for special cases.
Distribution of the outgoing correspondence to the local entities shall be made via messenger hand-delivery.  Facsimile distribution shall be warranted as necessary.
5.6.2         INCOMING LETTERS TO SITE OFFICE FROM THE CONTRACTOR
The Project Administrator shall registered all incoming document/mail, date stamp all item and forward to Project Manager for distribution to relevant discipline engineer . The correspondence concerning construction activities from the Contractor shall be addressed to:
Attention:      Imam Sucahyo, General Manager PT PLN (Persero) Unit Bisnis Pembangitan Sulmapa
Distribution of copies shall follow requirements in the Contract and BASCOM, as well as one copy distribution to the Project office.
5.6.3         CORRESPONDENCE BETWEEN PLN AND THE CONSULTANT
This section describes correspondence between PLN and the Consultants on the site matters, and technical matters that call for non-routine attention from the management of both PLN and the Consultants.
5.6.4         CORRESPONDEN BETWEEN CONSULTANTS TO PLN SITE OFFICE
The correspondence concerning construction activities and QA/QC from consultants to PLN Site office shall be addressed to:
Attention:      Imam Sucahyo, General Manager PT PLN (Persero) Unit Bisnis Pembangitan Sulmapa
The sample of correspondence show in Appendix 5.3
5.6.5         CORRESPONDENCE BETWEEN PLN TO CONSULTANT
The correspondence concerning construction activities from PLN to the Contractor shall be addressed to:
PT. REKADAYA ELEKTRIKA CONSULT
Jl. K.s Tubun I No. 2, Jakarta 11420
Up           : Mucklis Chaniago
Distribution of copies shall follow requirements in the Contract and BASCOM, as well as one copy distribution to the Project office.
The sample of correspondence show in Appendix 5.4
5.6.6         TELEPHONE CALL
Important telephone conference among the Project Team shall be recorded in the Telephone Call Notes (refer to Appendix 5.5).  Consultants’ interoffice memorandum shall not be handled by Procedure. All technical and contractual matters agreed upon by telephone shall be confirmated by fax or letter as soon as possible.
5.6.7         FAXCIMILE
Urgent matters shall be communicated via facsimile and or e-mail transmission among the Project Team. All outcoming and incoming shall be registered, originals shall be filled. The standar format of facsimilies is show in Appendix 5.6
5.7   MINUTES OF MEETING PROCEDURE
5.7.1         SCOPE MINUTE OF MEETING
All the Project related formal meetings between PLN site, Consultant and Contractor, PLN  and the consultant and others shall be recorded and registered in the Communication Control Register file.
5.7.2         RESPONSIBILITY
The Consultant’s Project team members shall be responsible for preparation of Minutes of Meeting for issue for acceptance by PLN, Contractor, and other entities attending the meetings. The Minutes of Meeting shall be prepared and issued promptly within a reasonable time, not exceeding two weeks from the time the meeting took place.
For the Weekly Meeting shall be conducted by all Engineers (Consultant project team) regarding with the discipline or duty of the Engineer. 
The Project site shall be responsible for logging Minutes of Meeting in the file and maintain the Register.


5.7.3         MINUTE OF MEETING
Minutes of Meeting prepared and issued by the Project Team but not include Engineering MOM, the record of meeting among PLN, the Consultant and the Contractor, and other MOM, the record of meetings on the consultant contractual scope, inspection construction and QA/QC.
a.      MOM Forms that are prepared and issued by the Project Team under this category shall follow the MOM Forms as shown in Appendix 5.7
b.      Preparation and Approval
The MOM shall be prepared by the Consultant Project Team during the meeting.  The MOM shall be reviewed, accepted and signed by the attendants from PLN, the Consultant and the Contractor after the meeting closed.
c.      Distribution
Immediately after signing, the MOM shall be distributed to representatives from PLN, the Consultant, the Contractor, etc.
5.7.4         MINUTE OF MEETING NUMBERS
Meeting Minutes are controlled by a unique MOM Number.  Project Team is responsible for maintaining sequential Meeting Minutes Number log and providing numbers as necessary.
5.7.5         COMMUNICATION CONTROL REGISTER MINUTE OF MEETING
The Communication Control Register Input for MOM shall be made at the time of preparing the Minutes.
5.7.6         MINUTE OF MEETING ACTION ITEMS CONTROL
Action items that are identified in the MOM are controlled by the Action Items Control using the Communication Control Register.  Only the designated significant
5.8   PROJECT FILING PROCEDURE
5.8.1         INTRODUCTION
This section describes the scope, responsibility and procedures for filing communications, minutes of meetings and documents in a centrally control manner.
5.8.2         SCOPE
All project related communications, MOM included documents are to be filed in centrally controlled files maintained the Site Office.
5.8.3         RESPONSIBILITY
Project Administration and or Project Team is responsible for establishing and maintaining complete record files, as well as maintaining reference files, for all project related communications, minutes of meetings and documents.

5.9   PROJECT FILES
5.9.1         COMMUNICATION FILES
Communication file contains documents that are assigned communication control numbers and processed.  The documents are filed in accordance with the Communication Control Number.  In addition, communications directly related to technical matters shall be filed in technical files as directed by lead discipline Engineers.  Exhibit as below shows a complete list of project files.
5.9.2         MINUTE OF MEETING FILE
Site Office and or Project Team are responsible for maintaining complete original MOM file for the minutes that are issued by the Project Team (site office).  All the revisions are also maintained in the file.  The originals shall be kept in the Record File Cabinet or Binders.  Site Office MOM shall also be included in the Meeting file although the originals of the Site Office Meeting Minutes shall be maintained by the Site Project administration and or Project Team
Site Office is responsible for maintaining complete original MOM file for the minutes that are issued by the Engineers.  All the revisions are also maintained in the file.  Originals shall be kept in the Record File Cabinet or Binders

Popular posts from this blog

Anggapan Al-Quran Sebagai Karangan Nabi Muhammad SAW

Ekstrimisme (Yang Dikutuk) Kita sekarang akan mengizinkan Roh Kebenaran untuk menempatkan Hantu dari orang Yahudi dan ekstrimis Kristen, dan membuat catatan tegas sehubungan dengan perbedaan mereka tentang Mesias. Orang-orang Yahudi berkata bahwa Yesus adalah anak tidak sah dari Maryam karena ia tidak dapat menunjukkan seorang ayah. Orang-orang Kristen dengan alasan yang sama membuatnya menjadi Tuhan dan anak keturunan Tuhan. Hanya cukup satu ayat saja untuk menolak kebohongan ini:  "Wahai Ahli kitab, janganlah kamu melampaui batas dalam agamamu, dan janganlah kamu mengatakan terhadap Allah kecuali yang benar. Sesungguhnya Al-Masih, 'Isa putra Maryam itu, adalah utusan Allah dan (yang diciptakan dengan) kalimat-Nya yang disampaikan-Nya kepada Maryam, dan (dengan tiupan) roh dari-Nya. Maka berimanlah kamu kepada Allah dan rasul rasul-Nya dan janganlah kamu mengatakan, '(Tuhan itu) tiga ; berhentilah (dari ucapan itu). (Itu) Lebih baik bagimu. Sesungguhnya Allah Tuhan...

PUMPS IS A MACHINE

INTRODUCTION A pump is a machine that imparts energy into a liquid to lift the liquid to a higher level, to transport the liquid from one place to another, to pressurize the liquid for some useful purpose, or to circulate the liquid in a piping system by overcoming the frictional resistance of the piping system. The pump is one of the oldest machines invented by man. The earliest pumps devised for raising water, such as the Persian and Roman waterwheels and the more advanced Archimedes screw, were invented to raise water from the hold of a ship. Since that time, many variations and applications of pumps have been developed, which in most cases can be classified into two basic methods used to impart energy to a liquid: volumetric or positive displacement, and addition of kinetic energy.

Belajar Dan Memahami Makna Wajah

Menarik sekali jikalau kita terus menerus belajar tentang fenomena apapun yang terjadi dalam hiruk-pikuk kehidupan ini. Tidak ada salahnya kalau kita buat semacam target. Misalnya : hari ini kita belajar tentang wajah. Wajah? Ya, wajah. Karena masalah wajah bukan hanya masalah bentuknya, tapi yang utama adalah pancaran yang tersemburat dari si pemilik wajah tersebut. Ketika pagi menyingsing, misalnya, tekadkan dalam diri : "Saya ingin tahu wajah yang paling menenteramkan hati itu seperti apa? Wajah yang paling menggelisahkan itu seperti bagaimana?" karena pastilah hari ini kita akan banyak bertemu dengan wajah orang per orang. Ya, karena setiap orang pastilah punya wajah. Wajah irtri, suami, anak, tetangga, teman sekantor, orang di perjalanan, dan lain sebagainya. Nah, ketika kita berjumpa dengan siapapun hari ini, marilah kita belajar ilmu tentang wajah. Subhanallaah, pastilah kita akan bertemu dengan beraneka macam bentuk wajah. Dan, tiap wajah ternyata dampaknya...