4.1 INTRODUCTION
This section describes methods and procedures for project
management comprising project co-ordination, progress reporting, management
reviews and review meeting, etc.
4.2 PROJECT EXECUTION METHOD AND MATRIX
This item defines the project organization and the
specific responsibilities for each of the areas of services of the Consultant
in accordance with the Contract No. ..................
The key areas of the Consultant’s services are:
1)
Contractor Interface - Support to PLN
in monitoring, and supervising Contractor's performance in construction and
commissioning.
2) Consultant - PLN Interface – Reporting on
Contractor’s progress of work and making recommendations to PLN if necessary
4.2.1
Division
of Responsibility
The division of responsibility for the scope of services
defined in Construction Supervision and QA/QC in accordance with Contract No. ...................................................................... with PLN .
4.2.2 Key Position Descriptions
The position descriptions of the key members of the Consultant’s
team :
-
Project
Director
-
Project
Manager
-
Boiler/Turbine
Engineer
-
BOP
Engineer
-
Coal
& Ash Handling Engineer
-
Electrical
Engineer
-
Instrument
&Control Engineer
-
Civil
Structure Engineer
-
Chemical
/ Environmental Engineer
-
Planning
/ Schedule Engineer
4.3 Interface between Consultant’s Head Office
and Site Office
The key interfacing between the Jakarta (Head Office) and
the Site Office is achieved by the following:
Consultant’s Project Manager – plays key role in
interfacing between Jakarta (Head Office) and Site Office activities and
provides coordination and direction as necessary to the personnel at each
location.
Coordination Meeting – The Consultant and Site Offices
have their own Weekly Coordination Meetings involving PLN, Consultant and the
Contractor.
4.4 Interfaces between Contractors
Interface with Contractor shall take place at Site
offices independently. With PLN’s
approval, the Consultant’s project team members may also initiate direct
contact with the Contractor for expediting any pending issues that need to be
resolved in a timely manner. PLN project
team members shall be notified of such direct contact by copy of
correspondence, telecom or facsimile communication.
4.5 Interfaces between PLN Organizations
Standard interfacing among PLN organizations
is through normal exchange of correspondence and documents in accordance with
BASCOM. Special interfacing if necessary
between different PLN entities will be initiated by PLN Pusat, PLN E, PLN
Pikitring SUAR or PLN Site depending on nature of interface and the
corresponding responsible PLN entity. Refer to BASCOM Exhibit as below
4.6 Engineer Site Activities and Meeting
The
Consultants Engineer (project team) has activities involving Inspectors to
monitoring and makes comments to the contractor’s activities against day by day
and will support to PLN Site and Project Manager. The form of Engineer activities
show in Appendix 4.1
4.7 Weekly meeting
The purpose of discussed site maters the consultant
Engineer lead weekly meeting regularly in every week involving PLN Site,
Consultant and Contractor at PLN site office. The form of weekly meeting show. The form weekly meeting show in Appendix 4.2
4.8
Monthly
Progress Report
This
section describes responsibility, issue schedule and contents of the Monthly
Progress Reports to report progress of the Consultant’s work to PLN.
4.8.1 Responsibility
The
Project Manager is responsible for the issue of the Monthly Progress Report
4.8.2 Issue Schedule
The
monthly report details activities for the period of the previous month. The monthly report shall be issued by the
Project Manager by the end of the following month if required
4.8.3
Content
Content
of Monthly Progress Report show in Appendix 4.3
4.9
QUATERLY
PROGRESS REPORT
Every third month, a quarterly Progress Report shall be
issued by the end of the following month.
The
report shall cover all activities during the quarter and be issued in a similar
way as the Monthly Report described in item 7 above
4.10
REVIEW
OF CONTRACTORS PROGRESS REPORT
The Consultant shall review the Contractor’s monthly
report and provide PLN with comments for further action.
4.11
PROJECT
COORDINATION MEETING
Following issues shall be addressed in the Project Coordination
Meeting to be held every other month at PLN Pembangkitan Sumatera I and or PLN
Head Office Jakarta and or PLN site.
-
Contractor’s
progress and performance
-
Technical
matters related Construction and or Engineering if necessary
-
Special
problems, if any
The form
weekly meeting show in Appendix 4.4
4.12
ASSIGNMENT
OF PERSONEL
The Consultant’s
personnel shall be assigned to the project.
5. ADMINISTRASION
PROCEDURES
5.1 GENERAL
5.1.1 Purpose
This
procedure is written with the aim of ensuring that information is channeled in
an appropriate manner. This procedure details administrative functions
associated with project communications.
It does not apply to Contractor’s engineering documents or to minutes of
meeting.
5.1.2 Scope and Application
This
procedure covers all forms of internal and external communications and applies
to all members of the Project.
The communication procedure applies to letters,
correspondence, transmittal, telephone communications between PLN Site and the
Consultants included PLN organizations, project team members and other
correspondence associated with the Project and proceed at the Construction Site
Office.
The control of communications is described in Appendix 5.1
and in the Communication Control Register Instruction Manual for the Project
This communication procedure does not apply to the
Contractor’s engineering documents such as design drawings, specifications and
calculations, which are controlled by the Design Document Register.
5.1.3 Updating and Issue
Updating and review of this procedure shall be
under-taken by the Project Manager as and when it is necessary.
5.2. DISTRIBUTION
5.2.1 Minimum Distribution
Originators or recipients of correspondence, telexes,
minutes of telephone call, etc. shall ensure that copies are distributed as
shown on the "BASCOM" sheet show in Appendix 5.1
5.2.2 Additional Distribution
5.3 RESPONSIBILITY
The Project Administrators involving Secretary who are in
charge of the Communication Control Register (Project Team) in the Project Site
Office, respectively shall be responsible for processing and controlling the
project correspondence, including distributing, retrieving and maintaining the
Project record files as well as reference files.
5.4 STANDARD FORM
The
Project standard communication forms are shown in Appendix 5.2 the Site Office
Project Standard Form respectively.
5.5 COMMUNICATION
PROCEDURE
This
section describes correspondence procedure for the Project correspondence with
the Contractor at the Site Office, correspondence between PLN and the
Consultants.
5.6 SITE OFFICE CORRESPONDENCE
5.6.1 OUTGOING LETTERS
a)
Formats
The
outgoing Site Office correspondence shall follow the sample letter formats and
letterhead in Appendix 5.2 Control Numbers
All
the outgoing letters from PLN Site to the Contractor shall have a PLN Site
stamp if any and PLN Site control number as well as a central communication
control number assigned by the Communication Control Register.
b)
Distribution
Distribution
shall follow the requirements of BASCOM in Appendix
5.1 or as directed by the originator for special cases.
Distribution
of the outgoing correspondence to the local entities shall be made via
messenger hand-delivery. Facsimile
distribution shall be warranted as necessary.
5.6.2 INCOMING LETTERS TO SITE OFFICE FROM
THE CONTRACTOR
The Project
Administrator shall registered all incoming document/mail, date stamp all item
and forward to Project Manager for distribution to relevant discipline engineer
. The correspondence concerning construction activities from the Contractor
shall be addressed to:
Attention: Imam Sucahyo, General
Manager PT PLN (Persero) Unit Bisnis Pembangitan Sulmapa
Distribution of
copies shall follow requirements in the Contract and BASCOM, as well as one
copy distribution to the Project office.
5.6.3
CORRESPONDENCE BETWEEN PLN AND THE
CONSULTANT
This
section describes correspondence between PLN and the Consultants on the site
matters, and technical matters that call for non-routine attention from the
management of both PLN and the Consultants.
5.6.4
CORRESPONDEN BETWEEN CONSULTANTS
TO PLN SITE OFFICE
The
correspondence concerning construction activities and QA/QC from consultants to
PLN Site office shall be addressed to:
Attention: Imam Sucahyo, General
Manager PT PLN (Persero) Unit Bisnis Pembangitan Sulmapa
The
sample of correspondence show in Appendix
5.3
5.6.5
CORRESPONDENCE BETWEEN PLN TO
CONSULTANT
The
correspondence concerning construction activities from PLN to the Contractor
shall be addressed to:
PT. REKADAYA ELEKTRIKA CONSULT
Jl. K.s Tubun I No. 2, Jakarta 11420
Up : Mucklis Chaniago
Distribution of
copies shall follow requirements in the Contract and BASCOM, as well as one
copy distribution to the Project office.
The sample of
correspondence show in Appendix 5.4
5.6.6
TELEPHONE CALL
Important
telephone conference among the Project Team shall be recorded in the Telephone
Call Notes (refer to Appendix 5.5). Consultants’
interoffice memorandum shall not be handled by Procedure. All technical and
contractual matters agreed upon by telephone shall be confirmated by fax or
letter as soon as possible.
5.6.7
FAXCIMILE
Urgent
matters shall be communicated via facsimile and or e-mail transmission among
the Project Team. All outcoming and incoming shall be registered, originals shall
be filled. The standar format of facsimilies is show in Appendix 5.6
5.7 MINUTES OF MEETING PROCEDURE
5.7.1 SCOPE MINUTE OF MEETING
All
the Project related formal meetings between PLN site, Consultant and
Contractor, PLN and the consultant and
others shall be recorded and registered in the Communication Control Register
file.
5.7.2 RESPONSIBILITY
The
Consultant’s Project team members shall be responsible for preparation of
Minutes of Meeting for issue for acceptance by PLN, Contractor, and other
entities attending the meetings. The Minutes of Meeting shall be prepared and
issued promptly within a reasonable time, not exceeding two weeks from the time
the meeting took place.
For
the Weekly Meeting shall be conducted by all Engineers (Consultant project team)
regarding with the discipline or duty of the Engineer.
The Project
site shall be responsible for logging Minutes of Meeting in the file and
maintain the Register.
5.7.3 MINUTE OF MEETING
Minutes
of Meeting prepared and issued by the Project Team but not include Engineering
MOM, the record of meeting among PLN, the Consultant and the Contractor, and
other MOM, the record of meetings on the consultant contractual scope,
inspection construction and QA/QC.
a.
MOM
Forms that are prepared and issued by the Project Team under this category
shall follow the MOM Forms as shown in Appendix 5.7
b.
Preparation
and Approval
The MOM shall be prepared by the
Consultant Project Team during the meeting.
The MOM shall be reviewed, accepted and signed by the attendants from
PLN, the Consultant and the Contractor after the meeting closed.
c.
Distribution
Immediately after signing, the MOM
shall be distributed to representatives from PLN, the Consultant, the
Contractor, etc.
5.7.4 MINUTE OF MEETING NUMBERS
Meeting
Minutes are controlled by a unique MOM Number.
Project Team is responsible for maintaining sequential Meeting Minutes
Number log and providing numbers as necessary.
5.7.5 COMMUNICATION CONTROL REGISTER MINUTE
OF MEETING
The Communication Control Register Input for
MOM shall be made at the time of preparing the Minutes.
5.7.6 MINUTE OF MEETING ACTION ITEMS CONTROL
Action
items that are identified in the MOM are controlled by the Action Items Control
using the Communication Control Register.
Only the designated significant
5.8 PROJECT FILING PROCEDURE
5.8.1 INTRODUCTION
This
section describes the scope, responsibility and procedures for filing
communications, minutes of meetings and documents in a centrally control
manner.
5.8.2 SCOPE
All
project related communications, MOM included documents are to be filed in
centrally controlled files maintained the Site Office.
5.8.3 RESPONSIBILITY
Project
Administration and or Project Team is responsible for establishing and
maintaining complete record files, as well as maintaining reference files, for
all project related communications, minutes of meetings and documents.
5.9 PROJECT FILES
5.9.1 COMMUNICATION FILES
Communication
file contains documents that are assigned communication control numbers and
processed. The documents are filed in
accordance with the Communication Control Number. In addition, communications directly related
to technical matters shall be filed in technical files as directed by lead
discipline Engineers. Exhibit as below
shows a complete list of project files.
5.9.2 MINUTE OF MEETING FILE
Site
Office and or Project Team are responsible for maintaining complete original
MOM file for the minutes that are issued by the Project Team (site office). All the revisions are also maintained in the
file. The originals shall be kept in the
Record File Cabinet or Binders. Site
Office MOM shall also be included in the Meeting file although the originals of
the Site Office Meeting Minutes shall be maintained by the Site Project
administration and or Project Team
Site
Office is responsible for maintaining complete original MOM file for the
minutes that are issued by the Engineers.
All the revisions are also maintained in the file. Originals shall be kept in the Record File
Cabinet or Binders